Search only in working time has no effect
Open, HighPublic3 Story Points

Details

Differential Revisions
D190: Trigger freeSlotsAvailable also for an empty result.
Ticket Type
Task
mollekopf raised the priority of this task from 40 to 60.
mollekopf set the point value for this task to 3.Jun 27 2016, 11:40 AM
knauss moved this task from Backlog to Doing on the Sprint 201626 board.Jun 28 2016, 5:12 PM

Can reproduce:
*create timeserices that removes complete working time for 10days (6-20 o'clock) (7 is enough) (as jane)

  • try to create a event with jane as attentee (as john)
  • the automatic schedualr suggest correct only time outside the working time

*selecteting only search in working houers do not change anything

*a fix is to make the searchtime so big, that at least one result is within the working hours.

knauss moved this task from Doing to Review on the Sprint 201626 board.Jun 28 2016, 5:54 PM
knauss moved this task from Review to Done on the Sprint 201626 board.Jul 1 2016, 1:27 PM
mollekopf moved this task from Restricted Project Column to Restricted Project Column on the Restricted Project board.Jul 14 2016, 11:07 AM
mollekopf raised the priority of this task from 60 to High.Jul 14 2016, 11:22 AM
pasik added a subscriber: pasik.Nov 25 2017, 2:29 PM